After a brief hiatus, the reconstruction of the Lafenwa/Rounder Road project, formerly known as the Lafenwa/Ayetoro/Olodo road project, has recommenced.
The contracted construction team has swiftly returned to the site with a commitment to complete the section leading to Rounder.
Here are the latest updates on the project:
1. **Scarification of Existing Failed Asphalt Surface:** This phase has been successfully completed, ensuring a solid foundation for further work.
2. **Removal of Unsuitable Material and Replacement:** Currently underway, this crucial step aims to replace inadequate materials with suitable ones, ensuring the road's durability and longevity.
Newslife will keep you updated as this vital infrastructure project progresses.